Why It Matters

Congress faces schedule, cost and architecture questions on the Artemis moon program, according to a new Congressional Research Service (CRS) report. ​

The National Aeronautics and Space Administration (NASA) requested $8.5 billion for Artemis systems for fiscal 2027, $731 million more than fiscal 2026 appropriations. Separately, Congress provided $6.7 billion for Orion, Gateway and the Space Launch System (SLS) through the fiscal 2025 reconciliation law, available through fiscal 2032.

The Trump administration's fiscal 2027 budget request also proposes replacing SLS with commercial transportation services after Artemis V.

The Big Picture

Artemis grew out of the NASA Authorization Act of 2010, which set a statutory goal of expanding permanent human presence beyond low-Earth orbit. It also mandated development of the Orion crew capsule and SLS. The NASA Transition Authorization Act of 2017 and Title VII of Public Law 117-167 make Artemis a stepping stone to Mars, and the latter directed NASA to establish a Moon to Mars Office.

Artemis II, the first crewed test of Orion and SLS, flew in April and carried four astronauts near the Moon. Artemis III, planned for 2027, is to demonstrate the SpaceX and Blue Origin landers by docking with a crewed Orion in Earth orbit. Artemis IV is planned by 2028 as the first human landing since 1972.

In March, NASA announced a phased Moon Base and an intended pause of Gateway, the planned lunar-orbit station. The shift follows Executive Order 14369, which calls for establishing initial elements of a permanent lunar outpost by 2030. NASA also plans to expand Commercial Lunar Payload Services, with a combined award value across two phases that it estimates at about $14 billion, against $2.6 billion for the first phase.

Advertisement

Oversight bodies have flagged some potential risks. A NASA Office of Inspector General report in March found that both lander providers have faced schedule delays and technical challenges that could affect costs and delivery, particularly for a 2028 landing. The Government Accountability Office estimated in a 2025 report that cost overruns for three major Artemis projects totaled $6.8 billion.

The Aerospace Safety Advisory Panel's 2025 annual report said lander complexity and delays "cast doubt" on the landing timeline. NASA is considering proposals from both providers to accelerate development.

The Bottom Line

Lawmakers could decide whether to shift Gateway funds to the Moon Base, and that choice would set which architecture the money supports as the 2028 landing target approaches.

No vote or deadline is named for the fiscal 2027 request or for the proposed move away from SLS.