Why It Matters
A Republican-backed bill that would allow certain power plants to move ahead of other projects waiting to connect to the electric grid has advanced toward a Senate vote, raising concerns that fossil fuel generators could receive preferential treatment over renewable energy projects.
The legislation would require the Federal Energy Regulatory Commission (FERC) to revise its interconnection rules to allow transmission providers to propose higher queue positions for dispatchable power projects, including certain fossil fuel plants. FERC would have 60 days to approve or deny each proposal. Supporters argue the change would improve grid reliability and ensure sufficient electricity generation, while critics warn it could allow natural gas plants to bypass renewable energy projects already waiting for grid connections.
The Big Picture
Sen. John Hoeven (R-ND) introduced the legislation Feb. 6, 2025, with Sen. Todd Young (R-IN) as an original cosponsor. The Senate Energy and Natural Resources Subcommittee on Energy examined the bill at an April 15 hearing alongside five other measures, published in the hearing record as S. Hrg. 119-366. The full committee ordered the legislation reported without amendment Sept. 30, and Chairman Mike Lee (R-UT) formally reported it Nov. 12 without amendment or a written report.
The April hearing also raised concerns about how federal regulators should determine which projects receive priority. One member warned against becoming "too prescriptive on the types of projects," which could undermine work already underway. A FERC witness emphasized that the commission "doesn't pick winners or losers" among electricity generation technologies.
The proposal comes as developers face lengthy delays connecting new power generation and storage projects to the grid. Lawrence Berkeley National Laboratory reported that nearly 2,600 gigawatts of generation and storage capacity were awaiting interconnection at the end of 2023 in its Queued Up: 2024 Edition. FERC's Order No. 2023 established a "first-ready, first-served" cluster-study process intended to reduce delays. The GRID Power Act would add a mechanism that allows certain dispatchable projects to receive higher priority in the interconnection process.
Partisan Perspectives
Sen. Martin Heinrich (D-NM), the committee's ranking member, criticized the legislation in an Oct. 6 statement, arguing that it would "codify 'queue jumping'" by allowing natural gas plants to connect to the grid ahead of clean energy projects. His criticism reflects concerns that prioritizing dispatchable generation could disadvantage renewable energy developers already waiting for interconnection approval.
Hoeven defended the legislation after the committee approved it, arguing it would help eliminate delays affecting the development of dispatchable power projects and strengthen electricity reliability. Young also promoted the bill in a Sept. 26, 2025, post on X, saying he introduced it "to promote energy independence and baseload power."
The Bottom Line
The GRID Power Act would require FERC to establish a process that lets transmission providers seek priority interconnection for qualifying dispatchable power projects, with a 60-day deadline for commission decisions. The legislation could accelerate connections for certain fossil fuel generators, although individual projects would still require regulatory approval.
The proposal faces political opposition over its potential effects on renewable energy development. All four Senate cosponsors are Republicans, and Heinrich has criticized its proposed queue-priority mechanism. However, the legislation has already advanced through the House: H.R. 1047 passed Sept. 18, 2025, by a 216-206 vote, with 211 Republicans and five Democrats voting in favor. The vote underscores the partisan divide over the proposal, despite limited Democratic support.
The April Senate hearing also considered five other bills addressing grid-enhancing technologies, FERC regulatory reviews, demand flexibility, cooling systems for artificial intelligence computing and reconductoring, placing the legislation within a broader congressional debate over electricity infrastructure and grid capacity.